02/24/2020 5:53 PM | Angela Petty (Administrator)

The RFP for the GC is out now and will be selected between March 27-April 15. 

We are currently in Schematic Design and will begin Design Development once the GC is selected. 

The site demolition of the dorms will not begin until Winter 2020, with an overall construction schedule of 18 months; however, we are optimistic in achieving an earlier completion date. 

We are requiring the GC to submit their fee, but price will not be a deciding factor. Rather, the score will be heavily weighted on technical requirements and team qualification. This is the first CMGC(Construction Manger/GC) early release bid for MTSU history! 

Although we have come a long way since conception, we still need more commitment to pledge a donation to our Alumni Donors Wall!! All of the larger rooms are named but we are looking to name some of the smaller spaces through these donations. More to come on this but in the meantime please help us spread the word to past and upcoming Alumni! 


CONTACT

Patron's President:

Daniel Bugbee | dbugbee@garrottbros.com

MTSU School of Concrete and Construction Management:

Sally Victory | 615/494-7658 | sally.victory@mtsu.edu

Powered by Wild Apricot Membership Software